PROJECT TYPE
Municipal
REGION/LOCATION
Powell River, BC
START DATE
September 2022
COMPLETION DATE
December 2022
SCOPE OF THE WORK
Plates were fabricated on site and welded onto the interior of the 14 foot penstock where the thickness was not to engineering standards. This work was all done on the inside of the pipe. All work was done using confined space procedures. The work had to be done in one shutdown and it was completed ahead of schedule.